Temporary Route 14 Closure Update: Progress Continues
Construction has been in full force to complete the temporary four-lane Route 14 roadway and the temporary two-lane Lake Zurich Road. Here’s what’s been happening behind the scenes over the past two weeks:
- Completion of grading, stone placement and temporary Canadian National Railway (CN) train track construction
- Shifting of train traffic onto the temporary CN tracks
- Utility main relocations
- Continued excavation, grading, compaction and construction of the temporary roadways and sidewalk
What’s still to come?
- Remaining grading and compaction work
- Asphalt installation for the temporary rail crossing
- Completion of both temporary road surfaces and lane line markings
The expected opening is still currently anticipated by the end of October.
Thank you for your continued patience and support of all Barrington businesses during this time.
Stay informed throughout the project by visiting the dedicated project website at www.us14underpass.com and signing up for email updates.