Project Update – May 13, 2026
The contractor has completed the installation of a new storm sewer and water main under the Canadian National railroad track, including making a connection to […]
....
Skip to content
The contractor has completed the installation of a new storm sewer and water main under the Canadian National railroad track, including making a connection to […]
Construction activity has ramped back up over the past month, with crews completing the following work: Completed the walls and bottom of the Route 14 […]
When the weather conditions permitted, construction activity continued through the winter months. Between January and March, crews completed the following work: Preparation for Permanent Sheeting […]
Construction activity has continued since Route 14 reopened on its new temporary four-lane roadway at the end of October. Over the past month, crews have […]
The Village of Barrington is excited to announce that Route 14 has officially reopened on its new temporary four-lane roadway, along with the temporary two-lane […]
Construction has been in full force to complete the temporary four-lane Route 14 roadway and the temporary two-lane Lake Zurich Road. Here’s what’s been happening […]
It has been a busy couple of weeks on the ground as we work towards opening up the temporary four-lane Route 14 roadway and the […]
This past month, almost all of the temporary Route 14 roadway and temporary railroad track was completed. The current lane closures on Route 14 allowed […]
This past month, significant progress was made in preparing the temporary Route 14 roadway and railroad tracks. Canadian National (CN) is working to install signal […]
.Construction continues on the U.S. Route 14 Underpass project, with the following work currently underway: Temporary road grading and paving Ongoing excavation for the pump […]