Project Update – Mid-June 2025
.Construction continues on the U.S. Route 14 Underpass project, with the following work currently underway:
- Temporary road grading and paving
- Ongoing excavation for the pump station
- Grading and preparation for a temporary railroad track
As part of the project, the Canadian National Railway (CN) is building a temporary parallel railroad track to allow trains to continue running while the new railroad bridge is constructed at the current crossing location.
To support this work, CN will deliver stone to the area by a specialized train. This stone will serve as the base for the new railroad ties and track. The delivery train is scheduled to arrive in Barrington next week, after making three stops before reaching the area.
During the stone delivery, which is expected to take several hours, the train will block the Lake Zurich Road crossing. Once the delivery is complete, the crossing will reopen. Once the confirmed train schedule is available, the Village will share updated traffic alerts via email and social media.
Looking ahead, paving work is planned for later this summer at the entry and exit points connecting the existing Route 14 pavement to the temporary roadway. This will require lane closures on Route 14, currently anticipated for mid-July. However, the exact timing depends on the progress of ongoing utility relocation efforts.
The Village will continue to provide updates as more information becomes available.