Project Update – December 2025
Construction activity has continued since Route 14 reopened on its new temporary four-lane roadway at the end of October. Over the past month, crews have […]
....
Skip to content
Construction activity has continued since Route 14 reopened on its new temporary four-lane roadway at the end of October. Over the past month, crews have […]
The Village of Barrington is excited to announce that Route 14 has officially reopened on its new temporary four-lane roadway, along with the temporary two-lane […]
Construction has been in full force to complete the temporary four-lane Route 14 roadway and the temporary two-lane Lake Zurich Road. Here’s what’s been happening […]
It has been a busy couple of weeks on the ground as we work towards opening up the temporary four-lane Route 14 roadway and the […]
This past month, almost all of the temporary Route 14 roadway and temporary railroad track was completed. The current lane closures on Route 14 allowed […]
This past month, significant progress was made in preparing the temporary Route 14 roadway and railroad tracks. Canadian National (CN) is working to install signal […]
.Construction continues on the U.S. Route 14 Underpass project, with the following work currently underway: Temporary road grading and paving Ongoing excavation for the pump […]
Construction on the U.S. Route 14 Underpass project is well underway. Over the past month, the contractor has: Coordinated excavation and grading work Made significant […]
On April 23, Village President Karen Darch, Barrington elected officials and staff welcomed local, county, state and federal leaders to break ground on the U.S. […]
This vital infrastructure improvement project will enhance traffic flow and safety in our community. Below are the latest updates: Grading Work: Topsoil removal and grading […]