Traffic Staging
Below are the approved stages for the maintenance of traffic during construction.
Beginning Stage — Anticipated Late Summer/Fall 2024
Prestage work will commence following award of the contractor and will begin with work on Hough Street to install a new culvert which will carry the rerouted Flint Creek. Demolition of 225 and 235 Elm Road will be completed and demolition of Willow Road will occur ahead of mass grading for the temporary roadway. Impacts to Willow Road will be delayed until necessary to facilitate the temporary roadway construction.